Ambulance Construction Progress Report #14
 
By Fire Chief Benjamin Nalborczyk
February 19, 2017
 

The New Ambulance is coming along the past weeks have been busy with getting the unit ready for service and this week will be just as busy meeting our target in service date of Saturday February 25th. We have completed the following task towards making the unit ready to serve:
- Custom made tool tray
- Knox Box Key Installation
- Custom Tool Mounting
- Equipment Stocking

This week the unit will be having lettering and graphics installed, final pre-service warranty work completed and MIEMSS inspection.

 
Units: A159